Ramco Cement plans expansion of its West Bengal Unit from 0.95 to 2.0 MTPA

Status : Pending for Environmental Clearance

Promoter : Ramco Cement Limited

Location : Kolaghat, West Bengal

Details : Current Status of the project is , it is waiting for ToR . According to MoEF sources proposal is to increase of the existing Grinding Unit from 0.95 MTPA to 2.0 MTPA by installing a new line .

Cost: The estimated cost of the project is Rs 250 Crores.

Completion: 18 months for construction after receipt of regulatory approvals.

Advertisements

Vigneshwara Cement plans expansion by additional 1×400 TPD grinding unit Bankura

Status : Environmental Clearance recommended

Promoter : Vigneshwara Cement Pvt  Limited

Location : Vill – Purandarpur, PO – Kanchanpur, PS & Dist – Bankura, West Bengal

Details : Current Status of the project is , it has been recommended for EC . According to MoEF sources proposal is to establish a new 400 TPD Grinding Unit for manufacturing PPC Cement. Total Expanded Capacity will be 0.18 MTPA

Cost: The estimated cost of the project is Rs 8.0 Crores.

Completion: 3 months for construction after receipt of regulatory approvals.

OCL plans to expand its Salboni unit to 4.0 MTPA

Status : Pending for Environmental Clearance

Promoter : OCL India Limited

Location : Vill Salboni, Dist. Pashchim Medinipur, West Bengal

Details : Current Status of the project is , it is waiting for ToR . According to MoEF sources proposal is to increase of the existing Blending Unit from 1.35 MTPA to 1.75 MTPA  and installation of 2.25 MTPA Vertical Roller Mill (VRM) based Cement Grinding Unit .

Cost: The estimated cost of the project is Rs 250 Crores.

Completion: 27 months for construction after receipt of regulatory approvals.

Proposed Expansion In Clinkerization Capacity from 1.98 MTPA to 3.20 MTPA by Emami Cement Ltd at Vill- Risda Chattishgarh

Status : Environmental Clearance obtained

Promoter : Emami Cement Limited

Location :  Villages- Risda & Dhandhani, Tehsil: Balodabazar, District- Balodabazar – Bhatapara, Chattishgarh

Details : Current Status of the project is , it has obtained EC . According to MoEF sources proposal is to expand the existing capacity of 1.98 MTPA to 3.2 MTPA Clinkerization Unit, and establishing  9 Waste Heat Recovery Boiler Power Plant. The excess clinker will be sent to its other sisters units in East India which are under construction .

Cost: The estimated cost of the project is Rs 1831 Crores.

Completion: 12-18 months for construction after receipt of regulatory approvals.